The installation of the booster pump water control automatic switch involves a series of steps. The following is a detailed installation guide compiled based on information provided by platforms such as Baidu AiGou: 1. Preparation before installation
1. Determine installation location: The automatic control switch for the booster pump should be installed at the outlet pipe of the water pump. To determine the position of the outlet of the booster pump and make corresponding decisions on the interface and fixed size of the automatic control switch of the booster pump. Choose a suitable opening position for the pipeline to connect the automatic control switch of the booster pump to the pipeline.
2. Check components: Ensure that all components (including gaskets, connectors, wires, etc.) are complete and intact.
3. Cleaning the pipeline: Ensure that the interior of the pipeline is clean and free of blockages. 2、 Installation steps
1. Connecting the pipeline: Align the cross-section of the pipeline with the interface of the automatic control switch, and select the appropriate sealing gasket and joint according to the diameter of the pipeline. Tightly fix the automatic control switch and pipeline together to ensure no leakage at the connection.
2. Wiring: Use copper wire or 2.5mm2 wire for wiring, and the wire should be a three core wire. Connect the three ends of the wire to the corresponding positions of the booster pump automatic control switch (usually including the live wire, neutral wire, and ground wire). After connection, protect the wires with tape or rubber hose to prevent leakage or short circuit.
3. Install regulating valves and pressure gauges: Install regulating valves on the inlet and outlet pipelines of the water pump to control water flow. Install a pressure gauge at the outlet to monitor the working pressure of the water pump. 3、 Debugging and Inspection
1. Turn off power: During wiring and installation, be sure to turn off the power supply of the booster pump to ensure safety.
2. Testing and Inspection: After installation, turn on the power switch and test and inspect the automatic control switch of the booster pump. Ensure that there is no water leakage or electric leakage, and that the wiring is connected correctly.
3. Set pressure value: Set the pressure value of the automatic control switch of the booster pump according to actual needs. When the water pressure reaches the set value, the switch should automatically turn off the booster pump; When the water pressure is lower than the set value, the switch should automatically start the booster pump. 4、 Precautions
1. Installation position: The installation position of the automatic control switch needs to be selected near the booster pump to avoid inaccurate water pressure control.
2. Sealing: When installing, it is necessary to choose sealing gaskets of the same specification and ensure that the connection is tight and leak free.
3. Wire connection: When wiring, do not string the small and large wire ends in series to ensure that the wire connection is firm and reliable.
4. Safe use: During use, the working status of the booster pump and automatic control switch should be regularly checked to ensure safe use.
By following the above steps and precautions, you can successfully install the booster pump water control automatic switch and achieve automatic control of water pressure. If necessary, it is recommended to consult a professional plumber for installation or commissioning.